top of page
  • Durham OnAir

New Elvet Bridge reopens in Durham City


Durham's New Elvet Bridge has reopened today following a full refurbishment.


The key city center bridge closed in July 2020 for essential works, including extensive

repairs to ensure the bridge remains structurally sound.


With work complete, the bridge is being reopened to all vehicles and pedestrians.


Diversions which were introduced to reduce congestion and manage traffic flow during the

bridge’s closure, including the bus gate at Quarryheads roundabout, will also be removed

later today.


During the 15-month project, significant structural concrete repairs saw the whole bridge

centre span lifted, the southern span of the bridge removed and replaced, and the bridge’s

joints removed, repaired and recast. Additional work to install a concrete protection

system, improved water proofing and drainage works were also undertaken to provide

extra protection for years to come.


A ribbon-cutting ceremony was held earlier this morning to mark the completion of the

project ahead of the bridge re-opening to traffic, whilst final checks were being completed.

Cllr Amanda Hopgood, Leader of Durham County Council, said: “I am delighted that work

on New Elvet Bridge is complete and that the route and associated diversions are now

open to all traffic once again.


“The bridge is a vital part of the city’s infrastructure and it needed urgent repairs to ensure

it remained safe to use. The completion of the project is a significant engineering

achievement.


“Issues such as the Covid pandemic and discovery of additional defects, which couldn’t be

identified in our initial investigations, have proved challenging but I’m pleased to say that

the project has gone well. Contractors and council staff have worked hard to complete not

only the planned essential works but also further work, which has reduced the need for

future maintenance and therefore minimised the need for future disruption.



“We’d like to thank the residents of Durham, its businesses and those who traveled

through the city, for their patience during the refurbishment.”


Dan Fawcett, project manager at Balfour Beatty, which was contracted to undertake the

work, said: “Our expert team has worked safely and efficiently to open this essential

bridge as quickly as possible.


“I would like to thank the public again for their co-operation and continued patience whilst

we undertook these essential repair works, which have restored an important transport link

in Durham City and will significantly benefit the community in the long-term.”

bottom of page